It’s November, and we’re well on our way to bringing the Dexter Ave property into the modern age. With fresh drywall, new doors and a new coat of paint, our construction team is really bringing this building back to life. Let’s discuss what we’ve been doing.

Keep reading for the details.

Scope of Work: Here is a breakdown of the progress on Dexter Ave since our last update.

    • Common area upgrades
      • Walls in the common area have continued to see a fresh coat of paint
      • Exterior lighting has been replaced, greatly increasing visibility for tenants
      • Entry door replacement has started taking place
      • Tree canopy trimming completed and we are starting the landscape design process
    • Increased structural support for roof deck in the ’02/’03/’04 stack

Window work was completed in the ’02/’03 stack

    • ’04 stack will be finished this week
  • Insulation has also begun in the ’02/’03 stack
  • Penthouse – framing is complete, plumbing and electrical has started

Financing: Our second draw with Seattle Bank will take place this week.

Additional Unit – Permit Update: Expectation is that we will hear from the review near the end of the calendar year with hopes to start this unit at the beginning of 2020.

What’s Next?: The following are projects to be completed over the next several weeks.

  • Railing install to continue through November
    Common area paint will continue through November
    Drywall and paint will be going into 9 of the units under renovation.
  • Common area paint will continue through November
  • Drywall and paint will be going into 9 of the units under renovation.
  • Railing install of glass paneling has started and will continue through November